Replacement of a complete glass-lined piping installation by a new one

This case study shows how De Dietrich Process Systems has managed the replacement of
a complete Glass-lined Piping intallation by a new one,
taking into account the stress analysis calculation, the manufacturing of the pieces and the installation on site.

 

CHALLENGES

The main challenge for us was to realize the job in a short period of time in order to reduce the shutdown period for the customer.

Other challenge for us: to be able to deliver a complete offer taken into account the complete scope of supply. As we are working with a subcontractor for the stress analysis report, we had to include this part in our complete quotation.

To discover the solution we have supplied, download the complete Case Study.

 

Contact us
Close
Case study download
Thank you to provide us some information before starting the download.
* Required fields

Les informations recueillies sur ce formulaire sont enregistrées dans un fichier informatisé par De Dietrich pour entrer en contact avec vous suite à votre candidature. La base légale du traitement est l’exécution de mesures précontractuelles.
Les données collectées seront communiquées aux seuls services compétents au traitement de votre demande chez De Dietrich.
Les données sont conservées la durée nécessaire à la réalisation des finalités pour lesquelles elles ont été collectées.
Vous pouvez accéder aux données vous concernant, les rectifier, demander leur effacement ou exercer votre droit à la limitation du traitement de vos données. Vous pouvez retirer à tout moment votre consentement au traitement de vos données.
Pour exercer ces droits ou pour toute question sur le traitement de vos données dans ce dispositif, vous pouvez vous adresser par courrier électronique à dpo@dedietrich.com
Si vous estimez, après nous avoir contactés, que vos droits « RGPD » ne sont pas respectés, vous pouvez adresser une réclamation à la CNIL.